IDEAL LINK TYPE FOR SUBCONTRACTOR ACTIVITY AND CLEARANCE

2 replies [Last post]
Hemanth Kumar
User offline. Last seen 43 weeks 2 days ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None

100 Rooms in a floor

"paint works" activity starts after clearance from main contractor

each room clearance is expected in different days

The plan is a floorwised one, having one single bar for "paint works " for a floor

how to secify the clearance in the plan?

as a milstone ? as a bar ? what should be the relationships ??

 

 

Replies

Hemanth Kumar
User offline. Last seen 43 weeks 2 days ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None

thank s mike

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Hemanth

The only way to do this properly is to break down the 100 rooms in each floor into sub groups in such number that the painters can work through them without interruption.

For instance if you are using 3 coat work then each room will have to be visited by a painter at least over 3 days.

So if you have 10 blocks of ten rooms and each room has a three day period then the duration for each floor can be broken down accordingly and the logic between rooms / blocks placed FS as required.

You will then have dates when:

1.  Each floor starts

2.  Each room / block starts

If you do not get permission to start on the programme dates you will have immediate information on progress and can report accordingly.

Best regards

Mike T.