High Level Planning Assignments

1 reply [Last post]
Ken Barrett
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 14 May 2007
Posts: 37

I have a fully resourced schedule completed. I am looking to run a report on the WBS level that will include the WBS name, The Budget for the WBS element, and the planning resources for that WBS element. I can not figure out how you assign a high level planning resource to the actual wbs element so that I can print off a nice report that states who will be the responsible manager/planner and controller for each wbs element

Any Help would be great!!

 

Ken

Replies

Joao Ribeiro
User offline. Last seen 5 years 34 weeks ago. Offline
Joined: 21 Mar 2003
Posts: 64

High Level resources just work in the Web version. You may achieve what you want by creating WBS type activities and assigne them the resources you want.

HTH

Joao