Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Assignment

1 reply [Last post]
Benito Bastone
User offline. Last seen 5 years 23 weeks ago. Offline
Joined: 15 Dec 2010
Posts: 3
Groups: None

Hi all,

Have been doing a lot of resourcing work & filtering a lot in the resource assignment tab. When i filter by my codes in the resource assignment I cant seem to save the filter like you normally can..... Any suggestions so I am not doubling up on setting up filters everytime i need to extract from the resource assignment tab?

Replies

Puneet Gupta
User offline. Last seen 10 years 13 weeks ago. Offline
Joined: 26 Apr 2005
Posts: 92

Which software are you working on?

 

Best Regards,

Puneet Gupta

Bau Management + Consulting GmbH