Activity date.

4 replies [Last post]
Shazia khan
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139

Hi Experts.

my schedule having 2 cal 5days and 6days,

Material activity finished date is 19 May-11 ( 5days Cal)

with rel.FS ,

Succe, Activity (Construction Activity with 6days cal) also starting at same date 19 May-11

Const.Acti. should be start next day means 20 May-11
(which is working day in cal)

according to Relationship,it should start on 20th May but it is not Please advise.


Thanks





Replies

Shazia khan
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139
once thanks for you valuable advise .

i have corrected , the cal timing and Activity moving to next day.

Thanks so much expert.
Rodel Marasigan
User offline. Last seen 19 hours 37 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Shazia,
Yes change the time to 5:00PM or what ever the end of working period and that should correct the timing including other successors timing. Also make sure that all durations are whole number by showing the digits on duration format. (Edit-> User Preferences-> Time Unit tab and under duration format, change the decimal to 2 so you can see all durations with decimal and change it to whole number.
Shazia khan
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139
Mr.Rodel

Thanks you are right , it was the same what you advise,

should i change my cal timing now. or any.

Thanks
Rodel Marasigan
User offline. Last seen 19 hours 37 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Shazia,
Check the time associated with your date. Material activity may finish 4:00PM instead of 5:00PM that is why Construction Activity starts on the same day.
(Edit-> Users Preferences-> Date tab. Under Time select 12:00 hour (1:30 PM) and tick show minutes)