Regarding Bar Color

4 replies [Last post]
Anbin Ponnith
User offline. Last seen 8 years 1 week ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear All,

Could any one specify the Standard Color code for all the bars used in Planning.

Eg. For Critical-Red


Thanks & Regards,

Anbin Ponnith

Replies

In Spider Project there is also an option when bar color is selected by the software basing on user defined conditions (signals, street lights, ...).
Most simple example: if activity is late its bar is red, if it is ahead of schedule the bar is green, if it is on schedule the bar is blue.
This option can be switched on and off.
Sometimes it is useful.

Best Regards,
Vladimir
Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Anbin

The general rule in respect of code colours applied to task bars is "less is better".

I use only four colours Green for level 4 tasks > Yellow for level 3 summaries > Cyan for level 2 and Dark Blue for level 1.

Avoid using multiple colours and patterns on tasks - it gives visual overload - the programme equivalent of a fireworks display.

Best regards

Mike Testro
Anbin Ponnith
User offline. Last seen 8 years 1 week ago. Offline
Joined: 8 Jun 2009
Posts: 158
Sir,
Thanks for your Reply

Regards
Anbin
Rodel Marasigan
User offline. Last seen 6 hours 25 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Anbin,
As far as my knowledge is concerned I haven’t read or encounter any ISO standard for Bar color on a Gantt chart.
By Default, Primavera use Green for outstanding activities, red for critical, blue for actual and yellow for baseline, MS Project use Blue for outstanding, red for critical and black for actual.
I know some company has define Standard Bar color for scheduling to avoid confusion and using same language when reading a schedule but for international or global none.