is it possible to give wt % to each activity in p6 and get total progress of the project according to this wt % age automatically ?

Replies

Rodel Marasigan
User offline. Last seen 1 day 21 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Manoj,
Yes you can weight your activities. Below link is a thread having same discussion.
Weighting % Post #2