Ethanol project period

5 replies [Last post]
Anu Tor
User offline. Last seen 13 years 15 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 53
Dear all members,

Could you instruct me the project period of Ethanol plant?
- Engineering = months
- Procurement = months
- Construction = months
The plant capacity is 100,000 million liters / year.

Thank you,

Replies

Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Trevor,

On average, the initial estimation would be withing 25% error. You are correct.

The best people to estimate the duration of the project, would be the Design team in association with skilled contractors who have done similar jobs in the past.

With kind regards,

Samer
Trevor Rabey
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
This top-down stuff is just pure guesswork, with a bit of experience thrown in, maybe. It doesn’t even rate as an estimate.

Could just as well be:

Engineering: 13 months
Procurement: 11 months
Construction: 23 months
Commissioning: 7 months

Plan the actual project in detail from the bottom up and then you know.
Jay S
User offline. Last seen 9 years 40 weeks ago. Offline
Joined: 10 Jun 2008
Posts: 36
Engineering 12 Months
Longest Lead I think is approx 12 Months (Vessel)Depended on Market
Construction - 6 to 9 Months
Commissioning 3 Months
This can overall as well to a certain Percentage I would say Overall approx 18 to 24 Months
The Biggest problem Process depends how far the design is or your inhouse capacity/Knowledge.
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Anu,

Very rough estimation, you can start with

Engineering: 12 months
Procurement: 12 months
Construction: 24 months
Commissioning: 6 months

Depending on the stage that you are at, you can float few inqueries for Engineering firms, suppliers and few Contractors with similar experiences in your area, and get more feedback.

With kind regards,

Samer
Shah. HB
User offline. Last seen 18 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi

Further more information regarding your long lead procurement is required.Plant projects generally driven mostly by long lead items ,it may not be 100% at least to some extent it is applicable