Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Revised Baseline

3 replies [Last post]
md ariff md thayoob
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 30 Apr 2005
Posts: 12
Groups: GPC Malaysia
Upon awarding a construction contract, the project manager shall ask for the contractor’s Baseline Programme. My query is can the contractor supersede the first baseline with a second (revised) baseline i.e the PM use this revised programme for monitoring progress instead of the original baseline. This is particularly so when the contractor is in delay and revises his construction method s in order to recover his delayed progress. Some call this revised baseline programme as Recovery Programme. Can we use this Recovery Programme as baseline programme i.e. to monitor his pgrogress? Thank you

Replies

md ariff md thayoob
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 30 Apr 2005
Posts: 12
Groups: GPC Malaysia
Appreciate, thanks
Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear MD,

The AACE is currently posting a draft Recommended Practice (RP) entitled: “Recovery Scheduling – As Applied in Engineering, Procurement and Construction”.

www.aacei.org

This subject is along the lines of your topic. You might want to read it and learn more how the revised baseline is prepared.

With kind regards,

Samer
Rafael Davila
User offline. Last seen 7 hours 52 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Superseeded only upon acceptance, still an agreement between two parties.

Baseline Schedule :( as defined under http://www.businessdictionary.com/definition/baseline-schedule.html , a kind of universal definition)

Fixed project schedule used in measuring project progress and contract performance. Any change caused by change in scope of the project invalidates the original schedule and necessitates a new baseline schedule.

From the following link you will find that a Recovery Programme upon acceptance shall become the new Baseline.

http://www.warnercon.com/articles/Article%2012%20-%20Recovery%20Schedule...

Acceptance might have the effect of a change in contract conditions; therefore both parties must be cautious.

Best regards,
Rafael