Irrigation Steel Water Tank

7 replies [Last post]
Anbin Ponnith
User offline. Last seen 8 years 4 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear All,

Can any one send me the program sequence for the Irrigation Steel Water Tank.(for L4 Schedule).


Thanks & Regards,

Anbin Ponnith

Replies

Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Anbin,

Please provide a copy to your construction team as well. You need to talk to them about the details and the sequence of work. They will have to build it for your. So, their opinion is a major criteria in the successful achievement of the Program of Works.

With kind regards,

Samer
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Anbin,

Please provide a copy to your construction team as well. You need to talk to them about the details and the sequence of work. They will have to build it for your. So, their opinion is a major criteria in the successful achievement of the Program of Works.

With kind regards,

Samer
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Anbin,

Please provide a copy to your construction team as well. You need to talk to them about the details and the sequence of work. They will have to build it for your. So, their opinion is a major criteria in the successful achievement of the Program of Works.

With kind regards,

Samer
Anbin Ponnith
User offline. Last seen 8 years 4 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear Samer,

Thanks a lot.I have submitted the program with all ur suggesions and remarks,,


With Thanks & Regards,

Anbin Ponnith
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Anbin,

This is a good start.
Please add the following at the start of the program:

1. Material submittals.
2. Shop drawings submittals.
3. Method Statements
Safety Plan
Erection Plan
4. Quality Records
Inspection and Testing Plan
Certification of Welders
Welding Procedures
5. Procurement: you need to mention the arrival of material at site.
6. At the end of the program you need to mention the Testing and Commissioning and Handing over to client.
A. "As Built" drawings
B. Quality Manual; inspection records, MTCs, Welding Maps, Test results.

7. Please show the installation of the Achor Bolts as an independent activity, because it will be handed over to client.
8. Have a look at the Electromechancial requirements of the project and make sure that you include them all.
9. Check the inspection requirements at site and include then in yoru construction sequence.
10. Check what is the height of the tank and how many plates you have and show them as levels in your construction sequence.

With kind regards,

Samer
Anbin Ponnith
User offline. Last seen 8 years 4 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Thanks Samer,

I have to submit the initial program to the client,

I have prepared in this way,
Irrigation Water Storage Tank 58 m Dia.

I.Sub Structure
Excavation & Compaction
ATT & Vapor Barrier
Blinding
Footing Rebar & Shuttering
Pour for Footing
Ring wall Rebar & Shuttering
Pour for Ring Wall
Water proofing
Backfilling
Cathode Ribbon & Conductor Bars
II.Super Structure
Laying of Bottom plate
Erection of Structural Columns
Erection of Girders
Erection of Rafters
Erection of Shell
Erection of Roof
III.Finishers
Erection of Staircase & ladder
Fixing of Nozzles
Cathodic Protection
Fixing of Accessories
Painting.

Please give me comments,

With Thanks & Regards,

Anbin Ponnith
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Anbin,

The following activities will help you with Building your schedule:

Site Activiites:
I. Substructure
Excavation
Blinding
Shuttering of Raft
Reinforcement of Raft
Anchor Bolt Setting
Casting of Raft

II. Super Structure
Erection of Steel Base
Welding of Plates (Level 1, 2, 3, etc)
Testing of Welds
Mechanical Fittings
Testing of Mechnical Fitting.
Electtrical installation.
Painting of Structure.
Installation of circulat ladders and handrails

III. Roof Installation
Scafolding or Lifting depending on the type of Roof.
Installation of circulat ladders and handrails
Testing of Welding
Painting

It would be highly recommended that you read the specifications, BOQs and Plans and include all the scope of work that you have in the Schedule of Work. Come up with a draft and show it to your team members, they will correct it and update you with the correct activities and sequence of works.

With kind regards,

Samer