Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

No Subject Specified

1 reply [Last post]
syed rafiuddin
User offline. Last seen 10 years 45 weeks ago. Offline
Joined: 20 Jun 2006
Posts: 12
Groups: None
Hi all.

can someone tell me how to get the values (in numbers) for labor units displayed on labor histogram per each time period (month or week) .

also the resource units are in days which is so uncomfortable to assess, is there a way to convert the units from days to numbers for labor resources

thanks & regards

Replies

Ferdinand Fincale...
User offline. Last seen 8 years 27 weeks ago. Offline
Joined: 2 Aug 2008
Posts: 140
Hello Syed,

In P5 or maye in P6, try to experiment by changing unit of hours, days, week, etc. of the Units Format and/or in the Duration Format in the User Preference dialog box particularly in the Time Units tab. See its result in the Resource Usage Spreadsheet if you are getting your desired result.

In Service,
Ferdinand