Auto Rule in P5

1 reply [Last post]
Anu Tor
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 7 Mar 2007
Posts: 53
How can I apply funtion " Link remaining duration and schedule percent complete " in P5

Replies

Arnold Puy
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Anu,

This feature is not supported in P5 & P6. However, you can use the % complete type, to do this try the following steps:

1. Highlight the activity you wanted to apply.
2. In Activity Details --> General Tab
3. In % Complete Type, select Physical
4. Go to Status in Activity Details, change the Physical % & Start/Finish Date
5. Hit F9 and that’s it.

HTH

Arnold