Clause 14 - Baseline

No replies
G. kumar
User offline. Last seen 6 years 38 weeks ago. Offline
Joined: 1 Jul 2004
Posts: 9
Groups: None
For a roads & bridges project, is it necessary to complete the trail trenches before submitting a meaningful baseline? And why the consultant delaying the approval of Clause 14