Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Carbon steel productivity rate

1 reply [Last post]
kier legard
User offline. Last seen 14 years 17 weeks ago. Offline
Joined: 31 Jul 2006
Posts: 96
Groups: None

Hi to all,

Does anybody what is the productivity rate for prefabrication and erection of carbon steel in Kgs.


Regards,
kier

Replies

kier legard
User offline. Last seen 14 years 17 weeks ago. Offline
Joined: 31 Jul 2006
Posts: 96
Groups: None
Hi to all


Are these values correct.

Activity description kg/mh
PREF.PIPING > 2 C.S.(AV.32,98) 55.55200327
U.G PIPING C.S. (AVE.32,98 IN) 33.0002508
ER.PIP.A.G.>2 C.S.(AV.32,98IN) 41.66403672


Regards
kier