No Subject Specified

5 replies [Last post]
Shahzad Ahmad
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi-All


any one suggest me in p3 how to increase lenght of bar in bar chrat. with increasing duration of activity.

i have set time scale months and week.


thanks

Replies

James Barnes
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 6 Sep 2007
Posts: 243
double click the yellow timescale at the top of the screen. In the dialog, you will see a slide bar labelled "Density". Silding that to the right will increase you bar lengths.

For printing, however, you need to play around with the settings in print preview. In there you can set the date range that will be displayed and this will be scaled to fit the page size you have selected. It’s quite powerful but takes some time to learn the ins and outs. Play around with it and you’ll be a pro in no time!
Shahzad Ahmad
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
i did that ...i set time scale ....Minimum Unit week.


..any other option is there..
Kamal Khemchandani
User offline. Last seen 6 years 36 weeks ago. Offline
Joined: 17 Nov 2007
Posts: 13
Groups: None
Hi shahzad,

Have you tried increasing the time scale

go to format>timescale
there you can set the density for the duration by moving the slider to the right.
The bars automatically look longer

voila
regards
Shahzad Ahmad
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Slam
I have a new project base line programme.

duration is very less naturally bar length is short,

i want to increase bar length with out increasing duration to make a presentable bar chart.

if there is any way to do so..

I am using P3...

Thanks
Shahzad Sikandar
User offline. Last seen 5 years 44 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
hi Shahzad

i dont undertand your question again sorry,,

when you increase duration, the lenghth of bar should automatically increase.

in it?

cheers