Weight percentages

7 replies [Last post]
Binish Toor
User offline. Last seen 16 years 2 weeks ago. Offline
Joined: 2 Mar 2008
Posts: 3
Please tell em the diffrence between :

1. Perecentage
2. weight percentage.
3. Weighatge

Replies

asyraf mr
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 11 Sep 2009
Posts: 9
Thanks Ronald..
Ronald Winter
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Yes, you can assign dates to Steps, but they will not ‘roll-up’ to your activity dates. Just add two User-Defined-Fields (UDF) to your Steps tab and make then data type: Date. Title the fields with “Start” and “Finish” or whatever you like. Good luck!
asyraf mr
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 11 Sep 2009
Posts: 9
in P6 i mean...
asyraf mr
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 11 Sep 2009
Posts: 9
Can we assign dates to the steps? it could be the planned or target dates to achieve the identified steps
Shahzad Sikandar
User offline. Last seen 5 years 44 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
Please ignore last two replies.
hope this one apears all right on the web page.

Percntage.


Is the amount of work done in terms of physical % complete or duration % complete or units % complete.
Whichever you are using in Primavera P5. value for this ranges between 0-100.

Weight Percentage and Weight.


Lets sey you have an activity which will be complete when A, B and C will be completed ( consider A, B and C as steps to that activity)

Now

You have to assign weight to each of this step,, how imp it is or what proportion of work it will cover for an activity

Just for an example.

Activity A
weight % = 40
weight = 2.0

Activity B
weight % = 40
weight = 2.0

Activity C
weight % = 20
weight = 1.0

When you change weight , percent weight should change automatically..

Lets suppose there are only 2 steps, so

Activity A
weight % = 50
weight= 2.0

Activity B
weight% = 50
Weight = 2.0

Hope this helps.

If I am incorrect please correct me.

Thanks

Keep asking and answering
Shahzad Sikandar
User offline. Last seen 5 years 44 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
Percntage.


Is the amount of work done in terms of physical % complete or duration % complete or units % complete.
Whichever you are using in Primavera P5. value for this ranges between 0-100.

Weight Percentage and Weight.


Lets sey you have an activity which will be complete when A, B and C will be completed ( consider A, B and C as steps to that activity)

Now

You have to assign weight to each of this step,, how imp it is or what proportion of work it will cover for an activity

Just for an example.

Activity steps weight (%) weight

Activity A 40 2.0
Activity B 40 2.0
Activity C 20 1.0

When you change weight , percent weight should change automatically..

Lets suppose there are only 2 steps, so

Activity steps weight (%) weight

Activity A 50 2.0
Activity B 50 2.0

Hope this helps.

If I am incorrect please correct me.

Thanks

Keep asking and answering
Shahzad Sikandar
User offline. Last seen 5 years 44 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None


Percntage.


Is the amount of work done in terms of physical % complete or duration % complete or units % complete.
Whichever you are using in Primavera P5. value for this ranges between 0-100.

Weight Percentage and Weight.


Lets sey you have an activity which will be complete when A, B and C will be completed ( consider A, B and C as steps to that activity)

Now

You have to assign weight to each of this step,, how imp it is or what proportion of work it will cover for an activity

Just for an example.

Activity steps percent weight (%) weight

Activity A 40 2.0
Activity B 40 2.0
Activity C 20 1.0

When you change weight , percent weight should change automatically..

Lets suppose there are only 2 steps, so

Activity steps percent weight (%) weight

Activity A 50 2.0
Activity B 50 2.0

Hope this helps.

If I am incorrect please correct me.

Thanks

Keep asking and answering