Resource Allocation

1 reply [Last post]
Shambhu Das
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 2 Apr 2005
Posts: 5
Groups: GPC Qatar
I am working as a Planner in a construction project. I am using P3 as a project planning tool. I want to put a number of resources (with quantity) in Left pan area for a number of activities. So, that I can say in a particular week, these are the activities to be excuted and their respective different sort of resources are also provided. This will help the construction site engineer to organise and plan for his next week’s programme with respect to materials as well as manpower also. I want the Gann chart in right pan as usual. How can I get this in P3 Window?

Replies

A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Shambhu,

Add custom data items for quantities. Thats most easy compared to adding budgeted quantity in resources tab.

Cheers,

Ravi