mporting revised project into base project

4 replies [Last post]
Vijayendra Surve
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 5 May 2007
Posts: 20
Groups: None
Sir,
how can be some activities of only specified floors imported into base project if two planners are working at the same time one for MEP & other for civil ,either one has to incorporate the things done in one project and make tht as base projject how can this be done .

Replies

J Venkatesh PMP P...
User offline. Last seen 10 years 46 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Hi Ramesh,

As I understood, If both planners are working on same project and one taking of civil and the other is taking care of MEP works..Updates for the same has been done by both of them, but on different projects...

U can try this...

Create and Assign filters Civil choosing only civil activties and MEP filtering MEP activities...Save the same as 2 two layouts respectively MEP and Civil...

Copy the file (2 files, 1 for Civil and 1 for MEP)issue the the same to planners and inform them to update in the respective layouts only...

after the updating, keep all the 3 files (Base, Copy - Civil, Copy - MEP) in a same folder..

Open the Base project, keep the Copy - Civil and Copy - MEP files as Target 1 and 2...

Keep anyone layout (Either Civil or MEP) as open, and go to Tools>Project Utilities>Target choose the respective target file (Either Copy - Civil or Copy - MEP)..Update Target for the selected layout only..By using this option, both the different files updated by the two planners, would be updated in the Base project...

Try this...If any doubts / confusion in this explanation, let me know...

Cheers

Venkat

Ramesh Kavassery
User offline. Last seen 6 years 4 days ago. Offline
Joined: 18 Oct 2004
Posts: 17
Groups: None
Hi Raviraj & Vijay,

I am not sure if copying and pasting would carry the
respective activity codes. Storing as a fragnet would
probably be better. I did face a problem earlier with
copy/paste. But fragnets neatly carry all the codes,
resources, links, etc. Only the activity IDs will have
to be changed as per new requirements, if any.

Happy Planning.....

Ramesh
A D
User offline. Last seen 3 years 20 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Vijay,

There is also tool available for merging (If you want to merge two projects and not few activities)

Go to Tools ---> Project Utilities ---> Merge

A D
User offline. Last seen 3 years 20 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Vijay,

Filter the activities required. Copy the required activties.

Select NO ACTIVTIES Filter. And then paste it into the new program. But, make sure activity codes defined in the previous program are also there in the new program.

Hope it works!!!

Cheers,

Raviraj