Manhours per discipline

3 replies [Last post]
muquith waseem
User offline. Last seen 6 years 37 weeks ago. Offline
Joined: 31 Jul 2006
Posts: 4
Hi

Can anyone help me that what is the standard Manhours allocated for the following
1) Structural per Ton
2) Piping Works per Ton or ID
3) E & I Works
4) Painting Works
5) Fireproofing Works


Cheers
Muquith

Replies

Berli Berli
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 20 Jun 2002
Posts: 19
Usually we used reference from old project. Allocation manhours are depend on works category i.e Piping works (Shop or field), Structural Works (Fabrication or Installation)etc...

Rgds,
Berli
Peter Holroyd
User offline. Last seen 6 days 3 hours ago. Offline
Joined: 6 Jun 2005
Posts: 160
start with the estimator - at least you will align with the manhours in the bid
Zhang Haixiang
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
different country/area has different standard