Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Program scheduling

3 replies [Last post]
irshath yakub
User offline. Last seen 14 years 40 weeks ago. Offline
Joined: 19 Jan 2004
Posts: 9
Iam a planner working in a infrastructure contracting company . The client wants only periodic updates of the project progress and i complete the monthly updates of the project progress. Activities which have been slipped results in new completion date.
Due to the slippage in the project progress,I could not able to exactly reorganise my schedule just because my schedule is time bound and not resource bound.
Please help me how to do a effective planning

Replies

Sukumaran Subaram...
User offline. Last seen 8 years 39 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Use some imaginary resources to recalculate the required duration to complete the job.

Example : if you need to start some activities concurrently to mitigate the delay, highlight to your project team the necessity to add in more resources to expedite the job.
With this additional resources work out the schedule and inform them the possible new completion date.

Regards.
Bernard Ertl
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
If you built a schedule using only date constraints and not logical relationships between tasks, then you are pretty much stuck unless you can get all stakeholders to agree to a new schedule IMO.

Bernard Ertl
eTaskMaker Project Planning Software
Zhang Haixiang
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
Hi,
what do you mean "I could not able to exactly reorganise my schedule".
delay is normal in project,trace the logic of your schedule,especially the critical path to find out what cause the delay,take corrective action if needed.

See what will happen next time you update the schedule