mile stone

2 replies [Last post]
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
can sombody define precisely milstone. also let me know the procedure for exporting file from excel to p3

Replies

Soheil Jafari
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 3 Jul 2001
Posts: 29
for import file from Excel to P3 you have to 2ways:
1- Save Activities Data to DBF format
2- Save Activities Data to WKs format(Lotus)
but be careful all header have to defined as per standard P3 field name.
Mark Lomas
User offline. Last seen 15 years 48 weeks ago. Offline
Joined: 27 Jun 2001
Posts: 177
Groups: None
Try this thread for a discussion on Milestone Schedules