I need your help guys. What is the different between retain logic and progress override. And what does it mean. How to use? thanks a lot

Replies

Sen Moc
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 30 Aug 2005
Posts: 123
Jiaparin (Kabayan!),

You are very welcome.

Regards.
Sen
Sukumaran Subaram...
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Hi,

Also go through P3 Help.
It explain the differences very well.

Regards.
Jiaparin Tumog
User offline. Last seen 4 years 33 weeks ago. Offline
Joined: 30 May 2003
Posts: 4
Sen Moc,

Really appreciated your soon reply for my question.
Sen Moc
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 30 Aug 2005
Posts: 123
Sen Moc
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 30 Aug 2005
Posts: 123
Brod,

Try the following internet link:

http://www.htcprojectcontrols.com/solbul.htm#Primavera%20Project%20Planner.

The Myths of "Out-of-Sequence" and "Retained Logic vs. Progress Override

Try also searching other threads in PP; this topic was already discussed here.

Regards.