P6 version issue? Edit, User Pref., Application - why do only some versions show "Codes" value vs description choice?

4 replies [Last post]
John Reeves
User offline. Last seen 18 weeks 1 day ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

I am using version 18.8 P6 version issue? Edit, User Pref., Application - why do only some versions show "Codes" value vs description choice?  I have seen snapshots on Linkedin of the choice "Specify how to display code values" - I do not get the choice and do not see a format column for the Value Description.  I can only show the value, which of the two is the less preferred.  I tried exclusive mode, no difference.  Any ideas why or how to correct.  Yes I can make a UDF but I have seen the option - just do not have it.  Perhaps they made it a column choice that I just do not see.

Replies

Andrew Podolny
User offline. Last seen 2 years 9 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130

John,

Check that you (your loign) have Admin Superuser privileges under Admin->Users.

Cheers

Zoltan Palffy
User offline. Last seen 11 weeks 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

Rodel is correct

however even in version 8.2 you can also go to edit user preference and under Group and sort select show id / code instead of show name / decsription

Rodel Marasigan
User offline. Last seen 8 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

This issue has been addressed in P6 version 20

Codes-Options

Zoltan Palffy
User offline. Last seen 11 weeks 11 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

I guess you can create another code and make the description the same as the code value

i.e.

responsibility 

code value    code description

civil              civil

 

I think that you can do it as a global change