Resource Movement Arrows Grayed Out

14 replies [Last post]
VIKAS KULKARNI
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 21 Feb 2020
Posts: 20
Groups: None

THE RESOURCE MOVEMENT ARROWS ARE GRAYED OUT - SO UNABLE TO MOVE THE RESOURCES - LEFT, RIGHT, UP OR DOWN.

EVEN IF I ADD NEW RESOURCES THE ARROWS STILL REMAIN GRAYED OUT.

STRANGELY IN BOTH THE LAPTOPS. WHY IS IT SO?

Replies

VIKAS KULKARNI
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 21 Feb 2020
Posts: 20
Groups: None

Thanks A Lot To Dear Mr. Zoltan Palffy too.

With The Very Best Regards.

VIKAS KULKARNI
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 21 Feb 2020
Posts: 20
Groups: None

Dear Mr. Alexandre Faulx-B & Mr. Santosh Bhat,

It worked - "The Resource Movement Blue Arrows" have appeared - Image Attached.

I had actually accidentially turned on the Resource Group & Sort by Primary Role. Therefore the Tri-State Toggle was alternating only between the first 2 states and not showing the third state i.e. 3 Lines -  Indent arrows - Hierarchical Structure.

I did not know that this Column Header is "A Tri-State Toggle".

Thanks A Lot To Both Of You,

With The Very Best Regards.

7658
tri-state_toggle_-_3_lines_-__indent_arrows_-_hierarchical_structure.png

Santosh Bhat
User offline. Last seen 17 hours 39 min ago. Offline
Joined: 15 Apr 2005
Posts: 331

Vikas,

 

The Column header for Resource ID is a Tri-State toggle. It can be clicked three times, once for sorting Ascending Alphanumerically, Again for Descending Alphanumerically, and thirdly for Hierarchically based on the Resource Structure.

Make sure you click this three times to go through each option and you should see the indent arrows appear when it is displaying the hierarchical structure.

VIKAS KULKARNI
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 21 Feb 2020
Posts: 20
Groups: None

Dear Alexandre Faulx-B,

7656
small_symbol_on_the_right_side_of_the_header_a.png

7657
small_symbol_on_the_right_side_of_the_header_b.png

I have pasted 2 Screen Shots of my my Resource ID Column Header.

If I click on the small triangle as shown in the upper image it gives the options as shown in the image &

if I click the small triangle as shown in the below image then P6 just Sorts the Resource ID's columns.

But there is no option where the small triangle changes to 3 lines.

Thanks & Regards.

 

VIKAS KULKARNI
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 21 Feb 2020
Posts: 20
Groups: None

Dear Alexandre Faulx-B,

7656
small_symbol_on_the_right_side_of_the_header_a.png

7657
small_symbol_on_the_right_side_of_the_header_b.png

I have pasted 2 Screen Shots of my my Resource ID Column Header.

If I click on the small triangle as shown in the upper image it gives the options as shown in the image &

if I click the small triangle as shown in the below image then P6 just Sorts the Resource ID's columns.

But there is no option where the small triangle changes to 3 lines.

Thanks & Regards.

 

 

Zoltan Palffy
User offline. Last seen 2 days 20 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2938
Groups: None

no they should not be greyed out I thinks it is a rights issue

 

go to Secuirty profiles make sure all of the Has Previleges boxes are checked for whatever profile Name is checked above.

VIKAS KULKARNI
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 21 Feb 2020
Posts: 20
Groups: None

Dear Mr. Santosh Bhat,

The filter is "ALREADY SET TO DISPLAY ALL RESOURCES".

I watched 2 YouTube Videos where the Presentor is also having these arrows grayed out in the video - So I think the Standalone Version seems to have these arrows grayed out - Maybe - I am not sure.

Thanks & Regards.

Zoltan Palffy
User offline. Last seen 2 days 20 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2938
Groups: None

not so sure of that 

Santosh Bhat
User offline. Last seen 17 hours 39 min ago. Offline
Joined: 15 Apr 2005
Posts: 331

Zoltan, SQLite databases don't have any user or security profiles - so those options wont be on the menu.

 

Its likely becuase the resource view is filtered. Select to display ALL RESOURCES and the arrows will appear.

Zoltan Palffy
User offline. Last seen 2 days 20 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2938
Groups: None

READ MY POST ITS UNDER

Admin

Security Profiles

VIKAS KULKARNI
User offline. Last seen 6 weeks 6 days ago. Offline
Joined: 21 Feb 2020
Posts: 20
Groups: None

Dear Sir,

Thanks for your reply.

I am using Primavera Standalone P6 Professional Release - 16.1 with PMDBSQLITE Database

The Admin Menu has only the following options -

1. Admin Preferences

2. Admin Categories

3. Currencies

4. Financial Periods

The other options i.e. -

1. Users

2. Security Profiles

3. Timesheet Dates

ARE MISSING

With Best Regards.

Zoltan Palffy
User offline. Last seen 2 days 20 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2938
Groups: None

make sure that you have the proper rigth to do this. It is lsited under the Admin Security profiles make sure all of the Has Previleges boxes are checked for whatever profile Name is checked above.