Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

F&D of an elevator? Average Fabrication & Delivery Time for a "New" elevator?

1 reply [Last post]
John Reeves
User offline. Last seen 10 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 342
Groups: None

F&D of an elevator?  Average Fabrication & Delivery Time for a "New" elevator?  I googled it - it said 6 months from time you hire consultant to deliverly.  Lets say for public project - I have seen 6 months just for F&D - what would be a reasonable duration to use?

PS, I think escalators are even longer - I think there are only 2 manufacturers in the Western World.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

90 to 120 days