SS+Lag plus FF+Lag

4 replies [Last post]
Sophia Gerami
User offline. Last seen 3 years 31 weeks ago. Offline
Joined: 4 Jul 2015
Posts: 2
Groups: None

I think we cannot have an activity with 2 relationships with the same successor activity(we need to decide the best logic) but my supervisor says we can have both SS+lag and FF+lag for one successor ! How can it be possible? it should be either SS+lag or FF+lag with the same successor. Do you agree or I'm wrong?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

this is known as a compound relationship and is common.

if you only use a SS this could happen

7515
compound.jpg

wysiwyg_imageupload::

Rafael Davila
User offline. Last seen 16 min 46 sec ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Rafael Davila
User offline. Last seen 16 min 46 sec ago. Offline
Joined: 1 Mar 2004
Posts: 5229

The risks of splitting activities that shall be executed continuously can be far more dangerous than pretending concurrent logic does not exists. This is specially true if your model is to apply resource constraints, it might spread apart the segments of an activity that shall be continuous. In such case use of SS(+lag) in combination to FF(+lag) relationships will make a better model.

Best Regards, Rafael

Santosh Bhat
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381

Sophia, this is a common technique to schedule activities that might happen in parallel, but where the second activitiy is delayed. 

Think for example if yoare digging a long trench, do you wait for the entire trench to be finished, before you start laying pipe? or can you start laying a pipe say once the trench has moved along by a distance? and in the same way, you cannot finish laying the pipe until some time after the trenching is completed.  so a SS/FF link to the same successory reflects this.

It might not pass the DCMA checklist, but in my opinion, that should not be a factor in determing whats realistic.