Dear All,
I have submitted the time schedule to the client without cost and resource uploaded.
Now client asked me to submit the schedule with cost and resources.
I have the some questions here,
1) From where i have to collect the cost of each activities. I asked one of my team member who has the priced BOQ ,but he said i cannot provide to you. I mean why he said so and what is the source of cost which i have to upload on P6?
2) Secondly, if i use the Priced BOQ, then how can i put the cost in activities separately, because in BOQ there is so much details of material and activities but in schedule we have simple and major activities.
3) Thirdly, Regarding resources use on site, how can i figure out how much we have to use labor, engineer etc and what about the cost of these labor?
4) If there is 50 labors working at a time on different activites, then should i have to add 50 resources in P6 separately?, and what about their names?
I would really appreciate if you reply me in Serial wise.
Thanks