Adding price for activities in order to get a cash flow

3 replies [Last post]
Ahmad Obeidat
User offline. Last seen 3 years 41 weeks ago. Offline
Joined: 26 Mar 2019
Posts: 15
Groups: None

Hello,

In my schedule, I didn't add any resources except for some materials.

Now I need cash flow for the project (revenue) on a monthly basis, how I can add prices for the activities ???

I have added the materials in order to get material usage on a weekly, monthly basis. 

I didn't add the labor resources because most of the works are subcontracted.

Regards,

Replies

Ahmad Obeidat
User offline. Last seen 3 years 41 weeks ago. Offline
Joined: 26 Mar 2019
Posts: 15
Groups: None

thank you 

Rafael Davila
User offline. Last seen 5 hours 17 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Loading cost in primavera schedule using resources and expenses r01 from Muhammad Mujahid PMP®, PSP®, SP®, APMC®
  • It looks like most software provide for the two options, learn both ways and make your choice.
Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

just add resource for the sub contractors call it lump sum and assign labor $ to each activitiy