(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Adding price for activities in order to get a cash flow

3 replies [Last post]
Ahmad Obeidat
User offline. Last seen 14 weeks 5 days ago. Offline
Joined: 26 Mar 2019
Posts: 13
Groups: None

Hello,

In my schedule, I didn't add any resources except for some materials.

Now I need cash flow for the project (revenue) on a monthly basis, how I can add prices for the activities ???

I have added the materials in order to get material usage on a weekly, monthly basis. 

I didn't add the labor resources because most of the works are subcontracted.

Regards,

Replies

Ahmad Obeidat
User offline. Last seen 14 weeks 5 days ago. Offline
Joined: 26 Mar 2019
Posts: 13
Groups: None

thank you 

Rafael Davila
User offline. Last seen 24 min 19 sec ago. Offline
Joined: 1 Mar 2004
Posts: 4765

Loading cost in primavera schedule using resources and expenses r01 from Muhammad Mujahid PMP®, PSP®, SP®, APMC®
  • It looks like most software provide for the two options, learn both ways and make your choice.
Zoltan Palffy
User offline. Last seen 2 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2335
Groups: None

just add resource for the sub contractors call it lump sum and assign labor $ to each activitiy