Loss of WBS Name when importing into P6 from MS Excel

3 replies [Last post]
Matthew Edwards
User offline. Last seen 3 years 21 weeks ago. Offline

Hi 

I am importing an MS excel file into P6. I have no issues with this.

However, when the excel file is imported, the WBS Name chages to the Master file name.

I cannot sort and filter the WBS in P6 as the WBS is lost.

Any help and suggestions would be appreciated.

Thanks

Matthew Edwards

Replies

Zoltan Palffy
User offline. Last seen 14 weeks 2 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

glad I could help 

Matthew Edwards
User offline. Last seen 3 years 21 weeks ago. Offline

Thanks Zoltan. !

Zoltan Palffy
User offline. Last seen 14 weeks 2 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

the first part of ALL wbs structure is ALWAYS the name of the Project ID this is what makes the activity id unique so that you can link different projects together that have the same activity id.

If the activities are already in there then just export them with the correct wbs

if the activites are not in there but the wbs is the easiest way to do this change the name of the projet to a single letter like the letter M

then when you add the activity the wbs will be M.whatever 

hope this helps