Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Budgeted Units

2 replies [Last post]
adab azeez
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
Greeting to all. Whenever I am adding a new resource to any activity in p6, the budgete units of all previously added resources are automatically changing. It drives me really crazy to put recorrect the budgeted value again and again.Can anyone advice why it is happening and how to prevent. Thanks in advance.

Replies

adab azeez
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
Thank you so much david
David Kelly
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Under Edit, User Preferences, Calculations:

Chose "preserve" rather than "recalculate"