Full of Constraints

4 replies [Last post]
Suhaib Nassar
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 25 Jun 2018
Posts: 13
Groups: None

As a bigenner planner, I have made a plan for a client as two projects, the start and finish dates for one of them are the actuals. whereas the start and finish dates of the other one are the planned ones, then I maintained the latter as a baseline to the first one, the client did not accept it and asked to modify that, he has also mentioned that the project is full of constaints. Are there any other ways to follow?

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Suhaib Nassar
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 25 Jun 2018
Posts: 13
Groups: None

Many thanks, the problem has been solved

Zoltan Palffy
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the only activities that should have constraints are CONTRACTUAL milestones

also the project must finish by date should be set