Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Performance % Complete Change After Assigning Baseline

6 replies [Last post]
Ahmad AbdRabou
User offline. Last seen 36 weeks 5 days ago. Offline
Joined: 10 Jun 2015
Posts: 20
Groups: None

I've Oracle Primavera P6 Professional R16.2

Project WBS contains 10 Major Items (Sites)

Contractor send update, I assign Baseline for compare Schd % against Perf %

the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one !

the remaining sites and the overall Perf % is the same, no changes, has no problem.

I need to know what happened.

Replies

Ahmad AbdRabou
User offline. Last seen 36 weeks 5 days ago. Offline
Joined: 10 Jun 2015
Posts: 20
Groups: None

I'll explain the problem in other words,

the contractor submitted an update

I loaded the udpate and checked for current progress %, it's 37.67%

then I loaded the baseline and checked the current progress % again to find that it's changed to 37.75%

what is the reason for that.

Zoltan Palffy
User offline. Last seen 2 days 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2399
Groups: None

a baseline is the planned % and NEVER chnages

the current schedule % complete will change based on progress

Ahmad AbdRabou
User offline. Last seen 36 weeks 5 days ago. Offline
Joined: 10 Jun 2015
Posts: 20
Groups: None

Can you Explain more so that I can test it.

Zoltan Palffy
User offline. Last seen 2 days 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2399
Groups: None

has to be something different ins the schedule

Ahmad AbdRabou
User offline. Last seen 36 weeks 5 days ago. Offline
Joined: 10 Jun 2015
Posts: 20
Groups: None

the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one !

for example:

Performance % Complete before assinging baseline is 37.67%

Performance % Complete after assinging baseline is 37.75%

do you know what happened?

Zoltan Palffy
User offline. Last seen 2 days 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2399
Groups: None

I would expect the performance % complete to changed based on what work got done or did not get done. Why would it stay the same that means that you did nothing