Performance % Complete Change After Assigning Baseline

6 replies [Last post]
Ahmad AbdRabou
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 10 Jun 2015
Posts: 20
Groups: None

I've Oracle Primavera P6 Professional R16.2

Project WBS contains 10 Major Items (Sites)

Contractor send update, I assign Baseline for compare Schd % against Perf %

the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one !

the remaining sites and the overall Perf % is the same, no changes, has no problem.

I need to know what happened.

Replies

Ahmad AbdRabou
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 10 Jun 2015
Posts: 20
Groups: None

I'll explain the problem in other words,

the contractor submitted an update

I loaded the udpate and checked for current progress %, it's 37.67%

then I loaded the baseline and checked the current progress % again to find that it's changed to 37.75%

what is the reason for that.

Zoltan Palffy
User offline. Last seen 11 hours 57 min ago. Offline
Joined: 13 Jul 2009
Posts: 1976

a baseline is the planned % and NEVER chnages

the current schedule % complete will change based on progress

Ahmad AbdRabou
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 10 Jun 2015
Posts: 20
Groups: None

Can you Explain more so that I can test it.

Zoltan Palffy
User offline. Last seen 11 hours 57 min ago. Offline
Joined: 13 Jul 2009
Posts: 1976

has to be something different ins the schedule

Ahmad AbdRabou
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 10 Jun 2015
Posts: 20
Groups: None

the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one !

for example:

Performance % Complete before assinging baseline is 37.67%

Performance % Complete after assinging baseline is 37.75%

do you know what happened?

Zoltan Palffy
User offline. Last seen 11 hours 57 min ago. Offline
Joined: 13 Jul 2009
Posts: 1976

I would expect the performance % complete to changed based on what work got done or did not get done. Why would it stay the same that means that you did nothing