primavera budgeted cost changes

2 replies [Last post]
müjdat özacar
User offline. Last seen 3 days 7 hours ago. Offline
Joined: 30 May 2009
Posts: 13

Hi All,

i assigned resources and cost to  my schedule ... but when i enter any actual date in the schedule budgeted total cost gets zero ..

before i didnt come across with this kind of situation.. your help will be appreciated.. 

thanks ina dvance

Replies

müjdat özacar
User offline. Last seen 3 days 7 hours ago. Offline
Joined: 30 May 2009
Posts: 13

Zoltan,

-my duration type is fixed duration & units.. i follow in that way

-actual units or cost that subtract actual from at completion is checked

-recalculate actual units and cost when duration % complete changes is unchecked because my activity % completion type is physical . i enter actual units or cost manually with real numbers

Zoltan Palffy
User offline. Last seen 3 days 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1724

make sure that the duration type is set to fixed duration and units/time

also go to PROJECTS and make sure that you project is highlighted and on the calculations tab make sure that under Resource assignments that When updating actual units or cost that subtract actual from at completion is checked and that recalculate actual units and cost when duration % complete changes.