Forum Sponsor:

Oracle Construction and Engineering (formerly Primavera) is transforming the world by helping organizations plan, build, and operate critical assets with on-premise and cloud-based project portfolio management solutions.  Learn more about Oracle Construction and Engineering...

We wish a warm welcome to the find people who are offering the ScheduleReader™ application. We hope to add more interesting news here shortly.

 

Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem as best as you can. Don't simply post "XYZ Isn't working". What is it you expected or wanted? What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera Baseline used bu Acumen Fuse

4 replies [Last post]
h m
User offline. Last seen 34 weeks 4 days ago. Offline
Joined: 10 Jan 2014
Posts: 5
Groups: None

Hi,

 

i'm struggling to undertsnad what baseline Acumen Fuse uses when we export from Primavera. I assumed it will be PROJECT BASELINE but even leaving that field set as Current Project it seems to be picking up a date (that isnt the current finish date).

Can someone explain it in laymans terms for me please.

 

Replies

Andrew Podolny
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 16 Nov 2004
Posts: 126

Use the Assign Baseline command and select the respective file to be assigned as the Baseline:

5484
clipboard-1.jpg

You will see the Symbol B after the Name of your Project in Acumen.

5485
clipboard-2.jpg

Regards,

Andrew

h m
User offline. Last seen 34 weeks 4 days ago. Offline
Joined: 10 Jan 2014
Posts: 5
Groups: None

Hi

seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

h m
User offline. Last seen 34 weeks 4 days ago. Offline
Joined: 10 Jan 2014
Posts: 5
Groups: None

Hi

seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

Zoltan Palffy
User offline. Last seen 20 hours 51 min ago. Offline
Joined: 13 Jul 2009
Posts: 2019

I would assume that you have to tell Acumen what schedule the basline is. Depending on the version of p6 the baseline even though attached DOES NOT come along with p6 export.

My guess is that Acumen wil be using the Late start and late finish dates as baseline dates if a baseline is not provided or identified.