Primavera Baseline used bu Acumen Fuse

4 replies [Last post]
h m
User offline. Last seen 22 weeks 4 days ago. Offline
Joined: 10 Jan 2014
Posts: 5
Groups: None

Hi,

 

i'm struggling to undertsnad what baseline Acumen Fuse uses when we export from Primavera. I assumed it will be PROJECT BASELINE but even leaving that field set as Current Project it seems to be picking up a date (that isnt the current finish date).

Can someone explain it in laymans terms for me please.

 

Replies

Andrew Podolny
User offline. Last seen 14 weeks 3 days ago. Offline
Joined: 16 Nov 2004
Posts: 126

Use the Assign Baseline command and select the respective file to be assigned as the Baseline:

5484
clipboard-1.jpg

You will see the Symbol B after the Name of your Project in Acumen.

5485
clipboard-2.jpg

Regards,

Andrew

h m
User offline. Last seen 22 weeks 4 days ago. Offline
Joined: 10 Jan 2014
Posts: 5
Groups: None

Hi

seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

h m
User offline. Last seen 22 weeks 4 days ago. Offline
Joined: 10 Jan 2014
Posts: 5
Groups: None

Hi

seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

Zoltan Palffy
User is online Online
Joined: 13 Jul 2009
Posts: 1915

I would assume that you have to tell Acumen what schedule the basline is. Depending on the version of p6 the baseline even though attached DOES NOT come along with p6 export.

My guess is that Acumen wil be using the Late start and late finish dates as baseline dates if a baseline is not provided or identified.