How to Remove All Relationships in Primavera P6

4 replies [Last post]
Emily Foster
User offline. Last seen 1 year 46 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Here's a fast and simple way to remove all relationships from the project schedule in Primavera P6 http://ed.gr/fxhn

Replies

Emily Foster
User offline. Last seen 1 year 46 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Hi Mike,

This was a quick tip in response to a customer question, so I thought I'd share it. I'm not really sure of the usefulness of doing this, but Hey Ho.

Cheers!

Emily

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

that only applies whne copying a project 

Mike, in Spider Project it is even easier 

Highlight all links (one mouse click), press Del and confirm that you are serious about this action (press OK).

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Emily

Apart from wondering why you would want to do such a thing it is much easier in Asta Powerproject in three taps.

Highlight link > ctrl a > delete and they are all gone.

Tap undo and they are all back.

Best regards

Mike T.