Summary of the filtered items in bar

2 replies [Last post]
Miranda Moonen
User offline. Last seen 23 weeks 6 days ago. Offline
Joined: 6 Oct 2017
Posts: 2
Groups: None

Hello ya'll,

I have a filter on my planning so I only see the items of my discipline. In none of the heading bars I can see the

correct summary of the items shown in my chosen layout.

Now I copy them to Excel so I can select the items I need to know.. But this doesn't work efficiently..

Anyone has the answer?

Thanks! Mi


Paul Kral
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 31 Aug 2017
Posts: 7

Try adding a UDF number field, enter "1" as value to your filtered results. Your grouping band should show the count (sum) of activities in your grouping.

Zoltan Palffy
User offline. Last seen 17 hours 24 min ago. Offline
Joined: 13 Jul 2009
Posts: 1696

how do u copy them ? highlight then then right click copy to excel  ?