Changing the Resource Type

1 reply [Last post]
Kannan CP
User offline. Last seen 6 days 19 hours ago. Offline
Joined: 12 Jun 2008
Posts: 280
Groups: None

In a Programme, all the equipments are assigned as Labor type, by mistake. While trying to change the type in the Resource Pool, it is showing the message as Not Possible to Change. Tried the Global Change and unsuccessful.

 

Any solution to rectify it.

Regards

Kannan

Replies

Zoltan Palffy
User offline. Last seen 2 days 13 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2540
Groups: None

copy existing resource info to excel 

create a new resource

delete old resource

assign new resource

export new resource and budgtes to excel

populate new resource budgets with info form old resource budgets

import new resoruce budgets