Check out our Assessment Centre and the Guild's Knowledge CAR and the Soteria Method

Progress Update

No replies
Mike Reymort
User offline. Last seen 1 week 5 hours ago. Offline
Joined: 24 May 2017
Posts: 6
Groups: None

I am updating my program on a weekly basis. Since my project is late my milestone dates are being delayed. The maximum delay for each milestone compared to the previous update should not exceed 7 days (since I am updating on a weekly basis). However, this is not the case; one of milestones got delayed for 9 rather than 7 days. How can my milestone be delayed more than 7 days if only 7 days had passed ? 

Any ideas ? 

 

Thanks

 

Mike