Has your question already been answered?

Get a quicker response; before you post, why not search to see if it has already been answered

Progress Update

2 replies [Last post]
Mike Reymort
User offline. Last seen 19 weeks 4 days ago. Offline
Joined: 24 May 2017
Posts: 7
Groups: None

I am updating my program on a weekly basis. Since my project is late my milestone dates are being delayed. The maximum delay for each milestone compared to the previous update should not exceed 7 days (since I am updating on a weekly basis). However, this is not the case; one of milestones got delayed for 9 rather than 7 days. How can my milestone be delayed more than 7 days if only 7 days had passed ? 

Any ideas ? 

 

Thanks

 

Mike 

Replies

Emad Mofarej,PMP,...
User offline. Last seen 6 weeks 4 days ago. Offline
Joined: 18 Feb 2012
Posts: 39

There are million explanations. As Zoltan said the usual suspect is the Calendar diffrence. specially when you are certain that you didn't change anything else and the diffrence is miniscule.

Here are some of the examples.

1-Calendar diffrence.

2- Holidays, Long weekens, winter restrictions etc

3- Modified logic, original durations, calendars, constraints

4- resource calendar

5- expected finish for in progress activities or extending at completion

 

 

If you are really interested to see what happened add the previous schedule update as the baseline. filter float path 1 and compare start and finish dates with each other along the line.

Zoltan Palffy
User offline. Last seen 13 hours 10 min ago. Offline
Joined: 13 Jul 2009
Posts: 1730

calendar difference