Updating over 7000 Activities in p6

1 reply [Last post]
Mohammad Zakaria
User offline. Last seen 6 years 3 days ago. Offline
Joined: 18 May 2017
Posts: 3
Groups: None

Hello Everyone,

I'v created baseling schedule contains over 7000 activities. I have to update them now by activity % complete. Is there and fast way to update them by excel if I have the data already in excel?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

yes export the activites to excel you will need to export the actual start field, actual finish field and either the remaining duration and or the duration % complete.

Progress 2 activities manually in P6 progress one that has started but has not yet finished and progress another one that has started AND finished use to see the format that is expected for the input data.

The actual start TIME and the actual finish TMES must be included in the import.