Scheduling Activities Just in Time for Its Successor

3 replies [Last post]
Sha Shajihan
User offline. Last seen 14 weeks 2 days ago. Offline
Joined: 5 Jan 2016
Posts: 8
Groups: None
I have equipment procurement activities that need to be delivered just in time for each install.  I place all the orders on Day 2 of the project.  I want to show, for each equipment, a lead time extending upto its install activity (its successor) starting on Day 3 upto Day X where X varies depending on the equipment. I am using P6 R16.2.  Using the ALAP constraint is an option, but using it for 15 activities? Any suggestions is most appreciated.

Replies

Zoltan Palffy
User offline. Last seen 3 days 7 min ago. Offline
Joined: 13 Jul 2009
Posts: 1819

glad I could help

Sha Shajihan
User offline. Last seen 14 weeks 2 days ago. Offline
Joined: 5 Jan 2016
Posts: 8
Groups: None

Thank you, Mr. Palffy, for your reply. 

Zoltan Palffy
User offline. Last seen 3 days 7 min ago. Offline
Joined: 13 Jul 2009
Posts: 1819

fro equipment delivery using the ALSP is acceptable