An sterisk on start or finish date

3 replies [Last post]
Carmen Arape
User offline. Last seen 6 years 36 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292

 

Hi All,

 

What does an asterisk shown on start or finish date of an activity mean??

I understood that this symbols comes up when the activity has a constraints date (any kind).

I have received an schedule with asteriks on start or finish dates without any constraints.

Appreciate any input,

Have a nice easter days,

Carmen

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Carmen Arape
User offline. Last seen 6 years 36 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292

Zoltan,

Thanks, dank u well, gracias.

That is the explanation... I am using the Construction schedule and contractor is building the CM commissioning schedule and making links...

REgards

 

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

There another possibility 

there is an external constraint meaning that this activity has a predecesor from a DIFFERENT PROJECT.