Drawbacks

2 replies [Last post]
Rama Chandran
User offline. Last seen 7 years 5 weeks ago. Offline
Joined: 18 Dec 2011
Posts: 10

Pls list out the drawbacks of Primavera. ( eg resource assignment can be done automatically depend on the resource availability)

Replies

I expected that people will respond to this very interesting question and discuss the way P6 can be improved.

Does weak response mean that everybody is happy with P6 capabilities?

Or it means that most people use P6 for drawing Gantt Charts and do not know about P6 project modeling drawbacks?

 

David Kelly
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

My top Four:

It does not have what Spider calls (I think) "Volume" per cent complete

WBS is project specific not Global

Top down planning cannot "nudge" the spending plan

No Cost window (like Resource Assignments but with the expenses)