Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Performance Percentage Completion ?

2 replies [Last post]
mostafa yousef
User offline. Last seen 7 years 4 weeks ago. Offline
Joined: 18 Feb 2017
Posts: 3
Groups: None

Hi, 

Performance percentage completion: On updating the P6 Program of works monthly (Jan 2017 to Feb 2017)overall percentage completion (Performance Pct Complete ) found to be decreased ,is there any reason behind it?

Regards,

Jossef

Replies

mostafa yousef
User offline. Last seen 7 years 4 weeks ago. Offline
Joined: 18 Feb 2017
Posts: 3
Groups: None

Thanks alot Kannan. As you said there was increment in the budget. 

 

Problem is now resolved. 

 

Thanks

Kannan CP
User offline. Last seen 2 weeks 6 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Mostafa,

Make sure that your Total Budgeted Cost is not increased. Also check if the previous month progress for any of the activities is reduced, as a correction.

Best Regards

Kannan