Estimate to Complete (ETC) Calculation

6 replies [Last post]
Lazy Bookwarm
User offline. Last seen 4 years 32 weeks ago. Offline
Joined: 17 Feb 2017
Posts: 6
Groups: None

Hi,

Estimate to Complete (ETC) values are not changing when I'm changing its calculation criteria under the WBS Earned Value settings. 

Following are the settings of my programme in P6

1) Duration type: Fixed duration and units

2) Percent complete type: Physical

3) Cost is assigned via labour resource.

Please help.

Thanks.

Replies

Lazy Bookwarm
User offline. Last seen 4 years 32 weeks ago. Offline
Joined: 17 Feb 2017
Posts: 6
Groups: None

Hi,

Settings under Project View->Calculations->Resource Assignments are as follows:

When updating actual units or cost -> subtract actual from at completion

"Recalculate actual units and costs when duration % complete changes" and "Link actual and actual this period units and cost" are ticked off. 

"Update units when costs change on resource assignments" is not ticked off

David Kelly
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

If you report Physical percent complete, then what mechanism are you using to reduce the remaining manhours/cost? 

How are you recording Actual Manhours/Cost?

Do you have any "Auto Compute" flags set at the Activity or Resource assignment level? 

How are you determining remaining duration AKA Duration % compete?

What are the settings in the "Resource Assigments" half of the "Calculations" Tab in the Project Details form?

Kannan CP
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

The actual cost for each activity may be still zero. So the ETC will remains the Budgeted Cost. Or in the WBS, change the setting as ETC=BAC-EV, PF=1.

Best Regards

Kannan

Zoltan Palffy
User offline. Last seen 8 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

change it to budgeted values with current dates 

Lazy Bookwarm
User offline. Last seen 4 years 32 weeks ago. Offline
Joined: 17 Feb 2017
Posts: 6
Groups: None

Technique for computing performance % complete: Activity % complete

Technique for computing Estimate to Complete: ETC= Remaining cost for activity

Earned Value Calculation: Budgeted values with planned dates

Zoltan Palffy
User offline. Last seen 8 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

in the Admin preferences what are your settings for Earned Value calculations ?