Bill,
What we have done form my platform job is create a material resource POB, where for each activity 10 hours = 1POB.
So if an activity has 200 hours made up of differing trades, then it has 20 POB.
Takes a small amount of time to set up, but realiatvely easy to import to P6 using Resource assignment import function.
Works for me. I use it for levelling beds.