planning units

4 replies [Last post]
abeer mohamed
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 6 Dec 2016
Posts: 3
Groups: None

dear all,

i created resource excavation budget is 22965 m3 at the beginning of the project & this budget by p6 divided as follows aug. 21872, at Oct. 608 & Nov. 216.

which is not appropriate for the project so i need to adjust it manual per month on P6 as follows:

aug. 10188, at Oct. 7139 & Nov. 5368.

please clarify how can i do it in steps especially the project is active and now i prepared the updated till end of Nov.

regards.

Replies

Zoltan Palffy
User offline. Last seen 3 days 13 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you have several options

option #1

break the actvity into 3 activites one that occures in Aug one that occurs in Oct and one that occurs in Nov then assign the units to the 3 activiites. What happend to September you totaly skip that month ?

option #2

create a custom curve and then assign that custom curve to that activity. Adjust the percentages in the custom curve to suit your needs. 

yalçın güner
User offline. Last seen 25 weeks 3 days ago. Offline
Joined: 9 May 2015
Posts: 16

P6 has divided your budgeted units according to its remaining duration. If you want to divide your budget free from duration you have to change your percent complete type I think.

abeer mohamed
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 6 Dec 2016
Posts: 3
Groups: None

i need to modify the budget per month manual not the actual or % complete

yalçın güner
User offline. Last seen 25 weeks 3 days ago. Offline
Joined: 9 May 2015
Posts: 16

Change your percent complete type from duration to Unit