No Admin Option in P16.1 ?

2 replies [Last post]
zahid shaikh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 24 Aug 2016
Posts: 35

No Admin Option in P16.1 ?

can anyone Guide me please

4405
capture-93.png

Replies

zahid shaikh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 24 Aug 2016
Posts: 35

Thanks

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

The windows client reconfigures itself depending on the version of the database you install it to.

 

With the EPPM database all of the admin tools are ONLY available in the web client

With the PPM database you get the Admin pull down.

No way round this......... Enjoy!