Combining works together

2 replies [Last post]
mohamed civil
User offline. Last seen 7 years 24 weeks ago. Offline
Joined: 2 May 2016
Posts: 14
Groups: None

There are two planning engineers in my company.We both have to create a baseline together for a building project.Now,I'm adding relationship of that project while he is assigning resources and costs for each activities.

Are there any methods to combine these two works together to submit our baselines to consultant?

If anyone knows,Please advice us.We have been using Primavera P6.7

Replies

Ayeni AdeDamola
User offline. Last seen 5 years 17 weeks ago. Offline
Joined: 5 Jun 2011
Posts: 5
Groups: GPC Qatar

Hi Mohammed, 

Alternatively - You can use the Whatif - Project reflection in Primavera -

Create Two Project Refelection from the Project - 

One to Add resources, the Other for your collegue - 

As required, all changes can be merges into the source project 

4256
primavera.png

 

 

 

Regards

Zoltan Palffy
User offline. Last seen 3 weeks 22 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you have 2 project sA and B

take the 1st project call it project B and expoort it to an xer file 

open project A and import project B into project A during the import process under import action select ADD to Existing