Resource Assignment

1 reply [Last post]
vigeeth salian
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 25 Feb 2016
Posts: 10
Groups: None

Hi guys,

 

I have an doubt regarding resource assignment.

the problem is,  i have to assign 2 manpower for 3activities.

this 2guys will only do that 3 activities.

how shall i assign to satisfy this condition.

can anyone explain step wise

 

Plz help.

Replies

Zoltan Palffy
User offline. Last seen 3 days 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

create a resource 

assign the resource to the activity

put the manhours required in the resource in the budgeted labor units 

done