activity resource templates

2 replies [Last post]
marco fulo
User offline. Last seen 8 years 9 weeks ago. Offline

Hi All,

Greetings...
 

Could anyone help me?  I'm new guy in primavera P6. It's there any activity resource templates in p6? Like Steps there is activity step templates which you can group a different step and easy to assign in each activities.  I have hundreds of activities need to assign a lots of resources and I’m having difficulties for adding or assigning them.

 

Thanks in advance for your help.

Regards,

Marco

Replies

wang chao
User offline. Last seen 1 year 13 weeks ago. Offline
Joined: 21 Mar 2011
Posts: 7

It's workflow function, according to the current revision funciton, it can't be generate automaticly, only be found by manual.

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can make a generic resource call it whatever LUMPSUM then filter for the activities that you want to add the resource to. 

select them all then rigth click and select assign then resource. THen you can export to excel and populate the spreadsheet with the manhours and or costs. Then import the spreadsheet back into P6