Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Planned Value Time Distributed Data Report

1 reply [Last post]
Simon Willson
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 1 Dec 2006
Posts: 68

Hi,

 

I need to run a time distributed planned value pull from my programme.  I have done these many times in the past albeit, a long time ago.  I tried to run the report against activities then the WBS (in the report wizard) but each time, the report returned a nill value. 

Appreciate guidance with this issue.

 

Thanks

 

Simon

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you mean manhours vs time ?

view show on bottom resource usage profile